2018 Spring Paving Schedule (weather permitting)

WEATHER PERMITTING, below is the anticipated 2018 paving schedule from Shields Asphalt Paving, Inc.

 

Foggy Hollow Rd, Hillcrest Dr, Haymont Dr, West Fenn Dr and Suncrest Dr:

Milling: To begin week of April 9th

Paving: Week of April 16th & 23rd


Grandview Dr (Rt. 8 to Grandview Estates North Plan) and Ridge Rd (Bakerstown Rd. to Kim Lane):

Milling:  To begin week of April 9th

Paving:  Week of April 16th & 23rd


King of Arms Dr, Dragon Rouge Dr, Lord Lyon Dr, Rex Norry Dr, St. Thomas Dr, Clarenceux Dr, and Stillwater Dr:

Milling:  To begin week of April 23rd

Paving:  To begin week of April 23rd


Forestwood Dr and Edgehill Dr:

Milling:  To begin week of April 23rd

Paving:  To begin week of April 30th


This project will be a significant upgrade to the existing roads.  Besides milling the full width of the road to a depth of approximately 3 1/2″, the contractor will test the strength of the road base and make any necessary repairs up to a depth of 12″.  Deteriorated storm drain inlets will be replaced or repaired.  Once the base work is complete, two layers of new asphalt will be installed.  After work is completed, Township road crew will back-fill against the curbs and restore the adjacent berm/lawn areas as soon as possible.

Due to their proximity to the edge of the pavement, some mailboxes will have to be moved.  During construction, the contractor will attempt to temporarily install the mailboxes.  Once construction is completed, the contractor will install the mailboxes in their permanent locations.  During construction, it is possible that mail and waste collection services may be disrupted.  Your patience in this regard is greatly appreciated.


During construction, please comply with the following:

  • NO ON-STREET PARKING DURING CONSTRUCTION.  It is critical that the paving machinery be able to move freely on the roadways.  If a vehicle is in the way, it will be towed.
  • Be sure to follow the flagmen’s instructions and work zone signage.
  • During the time between the milling and paving, motorists should take appropriate precautions to drive SLOWLY AND CAREFULLY to prevent damage to vehicles and surrounding property.
  • Please avoid driving on freshly paved surfaces.  Once marred, the quality of the paving job cannot be restored to its original standard.
  • The Township Engineer, Shoup Engineering, will be on-site during most project hours.  Any questions should be communicated with Shoup Engineering, not the paving crew workers.

As with any construction project, some inconveniences should be expected.  Although some traffic stoppage will be required, the contractor will try to keep it to a minimum.

Thank you for your patience!


 