2023 Street Paving Program
During the March 15, 2023 Board of Supervisor’s Public Meeting, the Supervisors accepted the lowest bidder, Shields Asphalt Paving, for the 2023 road paving program:
-
Heckert Road (Bakerstown Rd north to Parkview Estates Plan) - Complete -
Bellefield Court - Complete -
Corey Dr - Complete -
Woodhill Drive (Applewood to Lamont) - Complete -
High Meadows Dr - Complete -
Cider Mill Dr - Complete -
Blossom Dr - Complete - Greenspring Dr
- Madison Dr
- Meghan Ct
- Brooke Ct
- Banbury Crossing Rd
- Clendenning Rd (Grandview to Twp line)
- Dickey Rd (Meridian to Rt 8)
- McIntyre
Paving Updates and Information
5/5/23 Update - weather permitting:
- Monday, 5/8: Greenspring Drive, Madison Drive, Meghan Court, Brooke Court, Clendenning Road - Wearing Asphalt; VFD - Milling
- Tuesday, 5/9: Banbury Crossing, McIntyre Road - Wearing Asphalt; VFD - Binder and Wearing Asphalt; Dickey Road - Milling
- Wednesday, 5/10: Dickey Road - Milling
- Thursday, 5/11: Dickey Road - Binder Asphalt
- Friday, 5/12: Dickey Road - Wearing Asphalt
4/28/23 Update - weather permitting:
- Monday, 5/1: Woodhill Drive, Greenspring Drive - Milling; Cider Mill Drive, Blossom Drive, High Meadows Drive - Paving
- Tuesday, 5/2: Dickey Road - Milling; Woodhill Drive, Greenspring Drive - Paving
- Wednesday, 5/3: Dickey Road - Milling; Brooke Court, Meghan Court, Clendenning Drive, Heckert Road - Paving
- Thursday, 5/4: Woodhill Drive and Greenspring Drive - Binder Asphalt; High Meadows Drive and Cider Mill Drive - Wearing Asphalt
- Friday, 5/5: Woodhill Drive, Blossom Drive and Hecker Road - Wearing Asphalt
4/24/23 Update - weather permitting:
- Monday, 4/24: Brooke Court, Meghan Court, Clendenning Road - Binder Course; Banbury Crossing Road and McIntyre Road - Milling
- Tuesday, 4/25: Madison Drive, Banbury Crossing Road, McIntyre Road - Binder Course
- Wednesday, 4/26: Cider Mill Drive, Blossom Drive - Milling
- Thursday, 4/27: High Meadows Drive - Milling; Richland Park - Barn - Paving
4/20/23 Update - weather permitting:
- Friday 4/21: Corey Drive and Bellefield Court final wearing course. No milling.
- Monday 4/24: Meghan Court, Brooke Court and Clendenning Road binder course.
4/14/23 Update - weather permitting:
- Monday, 4/17: Milling - Brooke Court, Meghan Court and Clendenning Road (Grandview Drive to West Deer Township line); Binder Course Paving - Corey Drive and Bellefield Court
- Wednesday, 4/19: Binder Course Paving - Heckert Road
- Thursday, 4/20: Milling - Madison Drive
- Friday, 4/21: Binder Course Paving - Brooke Court, Meghan Court and Clendenning Road
4/12/23 Update - weather permitting: On Thursday, 4/13, milling will begin on Heckert Road (Bakerstown Road North to Parkview Estates Plan)
4/3/23 Update - weather permitting: Milling of roads is tentatively set for April 12th and will begin on Corey Drive and Bellefield Court, followed by Heckert Road
This project will be a significant upgrade to the existing roads. Besides milling the full width of the road to a depth of approximately 3 l /2", the contractor will test the strength of the road base and make any necessary repairs up to a depth of 12". Deteriorated storm drain inlets will be replaced or repaired. Once the base work is complete, two layers of new asphalt will be installed. After work is completed, Township road crew will back-fill against the curbs and restore the adjacent berm/lawn areas as soon as possible.
Due to their proximity to the edge of the pavement, some mailboxes will have to be moved. During construction, the contractor will attempt to temporarily install the mailboxes. Once construction is completed, the contractor will install the mailboxes in their permanent locations. During construction, it is possible that mail and waste collection· services may be disrupted. Your patience in this regard is greatly appreciated.
During construction, please comply with the following:
• NO ON-STREET PARKING DURING CONSTRUCTION. It is critical that the paving machinery be able to move freely on the roadways. If a vehicle is in the way, it will be towed.
• Be sure to follow the flagmen's instructions and work zone signage.
• During the time between the milling and paving, motorists should take appropriate precautions to drive SLOWLY AND CAREFULLY to prevent damage to vehicles and surrounding property.
• Please avoid driving on freshly paved surfaces. Once marred, the quality of the paving job cannot be restored to its original standard.
• The Township Engineer, Shoup Engineering, will be on-site during most project hours. Any questions should be communicated with Shoup Engineering, not the paving crew workers.
As with any construction project, some inconveniences should be expected. Although some traffic stoppage will be required, the contractor will try to keep it to a minimum.
Thank you for your patience!